The Ixonia LNG facility will be located in Jefferson County, Wisconsin in the town of Ixonia. The plant will be located approximately 5.7 miles southeast of the city of Watertown, Wisconsin and approximately 3.3 miles northwest of the city of Oconomowoc, Wisconsin.
The project includes a new LNG peaking facility, associated on-site pipelines and supporting equipment. The facility will be capable of liquefying, storing and vaporizing natural gas for peaking service.
Key project dates
Activity |
Time frame |
Construction start |
January 2022 |
Impoundment construction start |
March 2022 |
Tank foundation poured |
May 2022 |
Tank construction complete and commissioning begins |
Fall 2023 |
Project update
Construction of the Ixonia LNG plant continues to proceed on schedule.
Inside view of the Ixonia tank - welding ring #11 out of 13 total rings
LNG outer tank – welding vertical stiffeners
Previous updates
Core project (on-site) work hours
Monday to Friday
7 a.m. to 5 p.m.
Saturday* 7 a.m. to 5 p.m.
Sunday* 10 a.m. to 5 p.m.
*Only as necessary
Typical delivery hours
Monday to Friday
8 a.m. to 2:30 p.m.